What we do

Case study: Over looked excess and excessive costs?

Usually there isn’t an issue, and no indication of any over spend… unless you know what to ask and as importantly, who to ask.

Which was exactly the case when we were appointed by a client to manage a very large site with 30 plus meters and a spend approaching £1m a year.

Action

After reviewing the bills Argent Partnership requested an analysis of the kVA usage.

Result

A saving of over £20,000 which is on-going every year from implementation.

Our Services

Cost management

We go the extra mile to help our clients. Cost management is one of the ways we do it.

Our approach

Behind the technology,
there are great people too

Learn More